Aggarwal GlobalEmpowering Nation Enquire

Supply · Ladakh

Power Transformers in Ladakh

1 – 20 MVA. Delivery across Ladakh about 4 days by road, built to the specification your utility or project issues.

Range1 – 20 MVA
Deliveryabout 4 days by road
Standard1 – 20 MVA
Power transformer under assembly

Power transformer under assembly

01

Logistics and network

Supplying Ladakh.

Deliveries across Ladakh start at about 770 km by road, which puts the nearer cities (Leh) within 4 days of dispatch. The state's demand centres on Leh and Kargil, defence establishments, renewable park at Pang.

Distribution in Ladakh is handled by Ladakh Power Development Department; Ladakh Power Development Department runs the transmission network. Programmes now in execution include Ladakh 13 GW renewable project, grid connectivity works, and each is tendered against a technical specification that we quote and manufacture to.

02

The product

Power-class capability, in-house.

Full specification and gallery

The power transformer line closed the last gap in the chain. Between distribution and power class we now cover 16 kVA right through to 20 MVA — a span very few regional manufacturers hold on a single site.

The standard substation build is 33/11 kV, Dyn11, ONAN, with an off-circuit tap changer at +5% to −10%. Where the network needs voltage regulation under load we fit an on-load tap changer at +5% to −15%, and where the load profile justifies forced cooling we supply ONAF with a rated output at each cooling stage.

ParameterSpecification
Rated power1 MVA to 20 MVA
Typical ratings1 · 1.6 · 2 · 2.5 · 3.15 · 5 · 6.3 · 8 · 10 · 12.5 · 16 · 20 MVA
Voltage class33 / 11 kV; highest system voltage 36 kV
PhasesThree-phase
TypeOil-immersed, outdoor, core type — plain or corrugated tank; dry type to order
Frequency50 Hz standard; 60 Hz for export
03

Specifying

What changes for Ladakh.

  • Design ambient 35 °C, high altitude cold; seismic classification Zone IV for structures and foundations.
  • Inland exposure: standard epoxy-polyurethane exterior finish and hot-dip galvanized steel parts.
  • Temperature rise 45 K winding and 40 K top oil over the stated ambient, or 55 K / 50 K where Ladakh Power Development Department specifications allow; losses, impedance and tapping to the utility schedule or IS 1180 level.
FAQ

Questions

Frequently asked.

How long does delivery of Power Transformers to Ladakh take?
Road transit is about 4 days for a full load over roughly 770 km. Manufacturing time depends on the rating and quantity and is confirmed with the quotation.
Can you build to the Ladakh Power Development Department specification?
Yes. We quote against the utility's technical specification and guaranteed technical particulars, and routine tests are witnessed at our works by the purchaser or a third-party inspector before dispatch.
Do you supply private buyers and contractors across Ladakh, not only utilities?
Yes. Industrial plants, EPC contractors, solar developers, builders and dealers across Ladakh buy directly; send the schedule and we return a quotation with a delivery programme.

Send us your Power Transformers schedule for Ladakh.

Ratings, quantities, the specification you are buying against and the delivery point. We return a quotation with a firm delivery programme.